Glasgow Central’s £1.2m platform improvement project is on-track: GLC PLATFORM 1 TRACK UPGRADE (2)

Friday 28 Apr 2023

Glasgow Central’s £1.2m platform improvement project is on-track

Region & Route:
Scotland’s Railway: Scotland

A 10-week programme to renew track at Glasgow Central's platform 1 is progressing well.

Passengers travelling through Scotland’s busiest station will soon benefit from this £1.2m project to improve the track at platform 1 as part of efforts to enhance the safety and reliability of the railway for years to come.

Engineers have been on site since early March, removing rail along the length of the platform and breaking out sections of the concrete slab beneath.

More than 100 timber sleepers have been replaced with focus now turning to hanging and installing all 723 baseplates which sit under the rail and help keep it stable.  While we’re there, our teams also plan to renew signalling cables, clean the buffers and upgrade the tactile paving along the platform.

Platform 1 has been closed during the works, which began on 4 March 2023, with the project running alongside the existing closure of the West Coast Main Line (WCML) at Carstairs Junction to minimise the impact on passengers and is expected to open on time on 12 May.

And during the week, Liam Sumpter, Scotland’s Railway Route Director visited the team delivering this crucial work.

GLC PLATFORM 1 TRACK UPGRADE (3)

Liam Sumpter said: “These essential works at Glasgow Central station will ensure we continue to run a safe and reliable railway.

“Had we used normal access arrangements this work would be spread over a period of approximately four years’ worth of Saturday nights and would be considerably more costly. Instead, we’ve planned this 10-week programme to run at the same time as the closure of Carstairs Junction so that disruption to passengers is kept to a minimum.

“We have made some efficiencies in costs and timescales and have used this to allow for a deep clean of Platform 1 and removal of overgrown vegetation which is difficult to access during normal circumstances.

“We continue to thank passengers for their patience and understanding while we undertake these essential works.”

 For the latest information and progress updates follow on Twitter @NetworkRailScot.

Notes to Editors

For any questions on the article, contact:

Alison Clark-Dick
Communications Manager
Alison.Clark-Dick@networkrail.co.uk

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail Press Office - Monica McGinley
Communications Manager
Network Rail
monica.mcginley@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk